JN 174258 Demo Gas plant knockout drum 1000NB
ISO 9001 · LRQA Sun 9 Aug 2026
JN 174258 Closed Serial BJ-26-0258

Gas plant knockout drum 1000NB · Origin Energy · customer PO ORG-8812204 · AS 1210 Cl 1 · A516-70 · 100% NDE · witnessed by Bureau Veritas

From Q-26-0075
Contract value
$77,439
Ex GST
Progress
100%
Earned $77,439
Cost to date
$53,434
Labour $40,128 · material $13,306
Margin at completion
31.0%
$24,005 · 422.4 h forecast
Promised
29 May 2026
Despatched 9 Jun 2026
Hours
Quoted in two buckets and booked in the same two. Nothing routes through a work centre.
Labour
Manufacturing MFG Direct
376.0 of 387.0 h
Expected 387.0 h at 100% complete · -11.0 h
Testing TEST Direct
46.4 of 48.0 h
Expected 48.0 h at 100% complete · -1.6 h
Rework RWK Indirect
0.0 h
Named against this job so you can see it, charged against neither bucket so it never flatters the quote.
-12.6 h against expected Total direct booked 422.4 h of 435.0 h quoted.
Material bought against this job
The job carries the commitment from the day the order goes out, not the day the bill arrives.
Purchasing
Budget
$13,306
Committed
$0
Received
$0
Billed
$0
Against budget
$-13,306
ItemSpecificationQtyBudget
PL-CS-16Plate 16mm A516 Gr70 PVQ ASTM A516 Gr70 N · heat B-771318 18 m² $5,346
HD-CS-1500Dished end 1500NB A516-70 2:1 SE AS 1210 / ASME 2 ea $7,960
Paying the supplier happens through the job, so the cost lands on the job that caused it rather than in a general overhead bucket at the end of the month.
Quality
Register
NCRRaisedDispositionReworkStatus
NCR-2026-019Dished ends out of form tolerance on delivery 14 May 2026 Return to supplier closed
Invoiced
$77,439 of $77,439
InvoiceStageDueEx GSTStatus
INV-10874 Final 25 Jul 2026 $77,439 Paid
Customer
Origin Energy
Contact
Priya Naidu · priya.naidu@originenergy.com.au
Terms
30 days
Opened
2 Mar 2026
Promised
29 May 2026
Hydro
26 May 2026
Despatched
9 Jun 2026

Eleven days late. Dished ends arrived out of tolerance and were re-formed — NCR-2026-014.