A jobbing shop plans in weeks against promised dates, not in work-centre slots. Each bar runs from the day the job opened to the day it was promised, and the load underneath is the direct hours still to book against what the shop can turn out in a week.
Jobs on the floor
13
$1.48m of contract value
Direct hours remaining
4,884.0 h
Manufacturing and testing still to book
Shop capacity
394.0 h
11 on the tools, per week
Weeks of work
12.4
Remaining hours over weekly capacity
Due in six weeks
8
Promised on or before mid-September
The programme
Opened to promised, seven months across
Aug 26
Sep 26
Oct 26
Nov 26
Dec 26
Jan 27
Feb 27
The red line is today. A bar that has not reached it and is not filled is a job that needs hours on it this
week.
Due next
8 | Job | Customer | Promised | Days | Hours left | Progress | Status |
|---|---|---|---|---|---|---|
| JN 174305Air receiver 3000L Cl 150 — 4 off | Southern Compressed Air | 7 Aug 2026 | -2 | 78.5 | 100% | Ready for despatch |
| JN 174309Air receiver 5000L — Hallam | Southern Compressed Air | 8 Aug 2026 | -1 | 16.0 | 100% | Ready for despatch |
| JN 174287Ammonia chiller vessel 800NB — Adelaide | Cold Logic | 12 Aug 2026 | 3 | 100.0 | 96% | In test |
| JN 174331Wort cooler bundle replacement — Abbotsford | Carlton & United Breweries | 14 Aug 2026 | 5 | 45.0 | 94% | In test |
| JN 174298Reactor vessel 1200NB x 2400H SS316L | Viva Energy Refining | 28 Aug 2026 | 19 | 297.1 | 74% | In manufacture |
| JN 174312914Dia BEM Shell & Tube Exchanger — Altona crude unit | ExxonMobil Australia | 4 Sep 2026 | 26 | 558.9 | 62% | In manufacture |
| JN 174321Milk powder plant heat recovery unit | Nestlé Australia | 11 Sep 2026 | 33 | 326.5 | 48% | In manufacture |
| JN 174338Blast chiller vessel 900NB — Kilsyth | Scott Automation | 18 Sep 2026 | 40 | 222.0 | 31% | In manufacture |