b j britannia:jahco
b j britannia:jahco
JN 174264 Demo Kwinana lube oil cooler AES 610Dia
ISO 9001 · LRQA Sun 9 Aug 2026
JN 174264 Invoiced Serial BJ-26-0264

Kwinana lube oil cooler AES 610Dia · BP Australia · customer PO BP-AU-901255 · AS 1210 Cl 1 · TEMA AES · A516-70 / SS316L · 100% NDE · witnessed by Bureau Veritas

From Q-26-0079
Contract value
$138,875
Ex GST
Progress
100%
Earned $138,875
Cost to date
$89,202
Labour $49,866 · material $39,336
Margin at completion
35.8%
$49,673 · 524.9 h forecast
Promised
10 Jul 2026
Despatched 16 Jul 2026
Hours
Quoted in two buckets and booked in the same two. Nothing routes through a work centre.
Labour
Manufacturing MFG Direct
462.0 of 589.0 h
Expected 589.0 h at 100% complete · -127.0 h
Testing TEST Direct
55.9 of 70.0 h
Expected 70.0 h at 100% complete · -14.1 h
Rework RWK Indirect
7.0 h
Named against this job so you can see it, charged against neither bucket so it never flatters the quote.
-141.1 h against expected Total direct booked 517.9 h of 659.0 h quoted.
DateWhoCategoryHoursNote
15 Jul 2026 Ross Taylor Manufacturing 5.0
14 Jul 2026 Ross Taylor Manufacturing 1.5
13 Jul 2026 Marcus Keane Manufacturing 3.0
13 Jul 2026 Aftab Rahman Manufacturing 3.0
10 Jul 2026 Aftab Rahman Manufacturing 4.5
9 Jul 2026 Ross Taylor Rework 4.0 Weld repair / re-work to NCR
8 Jul 2026 David Nguyen Testing 7.5 Hydro / NDE witness / final dimensional
8 Jul 2026 Liam Farrell Manufacturing 3.0
8 Jul 2026 Harpreet Singh Manufacturing 4.5
7 Jul 2026 Harpreet Singh Manufacturing 3.0
3 Jul 2026 Tomislav Simić Manufacturing 3.0
2 Jul 2026 Brett Murray Manufacturing 7.0
1 Jul 2026 Liam Farrell Manufacturing 5.5
30 Jun 2026 Liam Farrell Manufacturing 2.0
Material bought against this job
The job carries the commitment from the day the order goes out, not the day the bill arrives.
Purchasing
Budget
$39,336
Committed
$0
Received
$0
Billed
$0
Against budget
$-39,336
ItemSpecificationQtyBudget
PL-CS-16Plate 16mm A516 Gr70 PVQ ASTM A516 Gr70 N · heat B-771318 16 m² $4,752
TU-316-1905Tube 19.05 x 1.65 SS316L seamless ASTM A213 TP316L · heat SV-884120 720 m $30,096
HD-CS-711Dished end 711NB A516-70 2:1 SE AS 1210 / ASME · heat SDH-40772 2 ea $2,560
FL-CS-600Flange 600NB WN A105 Cl150 RF ASME B16.5 · heat EZ-99402 2 ea $1,928
Paying the supplier happens through the job, so the cost lands on the job that caused it rather than in a general overhead bucket at the end of the month.
Quality
Register
NCRRaisedDispositionReworkStatus
NCR-2026-020Hardness survey above limit on PWHT coupon 28 May 2026 Rework 14.0 h closed
Data report issued 16 Jul 2026 — 9 of 9 sections complete · registration VIC-PE-118204.
Invoiced
$138,875 of $138,875
InvoiceStageDueEx GSTStatus
INV-10884 Final 31 Aug 2026 $138,875 Paid
Customer
BP Australia
Contact
Dean Mallory · dean.mallory@bp.com
Terms
45 EOM
Opened
13 Apr 2026
Promised
10 Jul 2026
Hydro
9 Jul 2026
Despatched
16 Jul 2026

Six days late. Tube supply slipped 11 days — see the supplier performance report.