JN 174264 Demo Kwinana lube oil cooler AES 610Dia
ISO 9001 · LRQA Sun 9 Aug 2026
JN 174264 Invoiced Serial BJ-26-0264

Kwinana lube oil cooler AES 610Dia · BP Australia · customer PO BP-AU-901255 · AS 1210 Cl 1 · TEMA AES · A516-70 / SS316L · 100% NDE · witnessed by Bureau Veritas

From Q-26-0079
Contract value
$138,875
Ex GST
Progress
100%
Earned $138,875
Cost to date
$89,202
Labour $49,866 · material $39,336
Margin at completion
35.8%
$49,673 · 524.9 h forecast
Promised
10 Jul 2026
Despatched 16 Jul 2026
Hours
Quoted in two buckets and booked in the same two. Nothing routes through a work centre.
Labour
Manufacturing MFG Direct
462.0 of 589.0 h
Expected 589.0 h at 100% complete · -127.0 h
Testing TEST Direct
55.9 of 70.0 h
Expected 70.0 h at 100% complete · -14.1 h
Rework RWK Indirect
7.0 h
Named against this job so you can see it, charged against neither bucket so it never flatters the quote.
-141.1 h against expected Total direct booked 517.9 h of 659.0 h quoted.
DateWhoCategoryHoursNote
15 Jul 2026 Ross Taylor Manufacturing 5.0 —
14 Jul 2026 Ross Taylor Manufacturing 1.5 —
13 Jul 2026 Marcus Keane Manufacturing 3.0 —
13 Jul 2026 Aftab Rahman Manufacturing 3.0 —
10 Jul 2026 Aftab Rahman Manufacturing 4.5 —
9 Jul 2026 Ross Taylor Rework 4.0 Weld repair / re-work to NCR
8 Jul 2026 David Nguyen Testing 7.5 Hydro / NDE witness / final dimensional
8 Jul 2026 Liam Farrell Manufacturing 3.0 —
8 Jul 2026 Harpreet Singh Manufacturing 4.5 —
7 Jul 2026 Harpreet Singh Manufacturing 3.0 —
3 Jul 2026 Tomislav Simić Manufacturing 3.0 —
2 Jul 2026 Brett Murray Manufacturing 7.0 —
1 Jul 2026 Liam Farrell Manufacturing 5.5 —
30 Jun 2026 Liam Farrell Manufacturing 2.0 —
Material bought against this job
The job carries the commitment from the day the order goes out, not the day the bill arrives.
Purchasing
Budget
$39,336
Committed
$0
Received
$0
Billed
$0
Against budget
$-39,336
ItemSpecificationQtyBudget
PL-CS-16Plate 16mm A516 Gr70 PVQ ASTM A516 Gr70 N · heat B-771318 16 m² $4,752
TU-316-1905Tube 19.05 x 1.65 SS316L seamless ASTM A213 TP316L · heat SV-884120 720 m $30,096
HD-CS-711Dished end 711NB A516-70 2:1 SE AS 1210 / ASME · heat SDH-40772 2 ea $2,560
FL-CS-600Flange 600NB WN A105 Cl150 RF ASME B16.5 · heat EZ-99402 2 ea $1,928
Paying the supplier happens through the job, so the cost lands on the job that caused it rather than in a general overhead bucket at the end of the month.
Quality
Register
NCRRaisedDispositionReworkStatus
NCR-2026-020Hardness survey above limit on PWHT coupon 28 May 2026 Rework 14.0 h closed
Data report issued 16 Jul 2026 — 9 of 9 sections complete · registration VIC-PE-118204.
Invoiced
$138,875 of $138,875
InvoiceStageDueEx GSTStatus
INV-10884 Final 31 Aug 2026 $138,875 Paid
Customer
BP Australia
Contact
Dean Mallory · dean.mallory@bp.com
Terms
45 EOM
Opened
13 Apr 2026
Promised
10 Jul 2026
Hydro
9 Jul 2026
Despatched
16 Jul 2026

Six days late. Tube supply slipped 11 days — see the supplier performance report.