b j britannia:jahco
b j britannia:jahco
JN 174287 Demo Ammonia chiller vessel 800NB — Adelaide
ISO 9001 · LRQA Sun 9 Aug 2026
JN 174287 In test Serial BJ-26-0287

Ammonia chiller vessel 800NB — Adelaide · Cold Logic · customer PO CL-2026-337 · AS 1210 Cl 2A · A516-70 · 25% NDE · witnessed by Bureau Veritas

From Q-26-0096 ITP
Contract value
$59,710
Ex GST
Progress
96%
Earned $57,322
Cost to date
$31,465
Labour $23,085 · material $8,380
Margin at completion
44.9%
$26,793 · 253.1 h forecast
Promised
12 Aug 2026
3 days to go
Hours
Quoted in two buckets and booked in the same two. Nothing routes through a work centre.
Labour
Manufacturing MFG Direct
213.5 of 298.0 h
Expected 286.1 h at 96% complete · -72.6 h
Testing TEST Direct
29.5 of 45.0 h
Expected 43.2 h at 96% complete · -13.7 h
Rework RWK Indirect
0.0 h
Named against this job so you can see it, charged against neither bucket so it never flatters the quote.
-86.3 h against expected Total direct booked 243.0 h of 343.0 h quoted.
DateWhoCategoryHoursNote
7 Aug 2026 Tomislav Simić Manufacturing 4.5
7 Aug 2026 Craig Carter Manufacturing 7.5
7 Aug 2026 Harpreet Singh Manufacturing 5.5
6 Aug 2026 David Nguyen Testing 5.0 Hydro / NDE witness / final dimensional
5 Aug 2026 Harpreet Singh Manufacturing 3.5
4 Aug 2026 Tomislav Simić Manufacturing 6.0
3 Aug 2026 David Nguyen Testing 4.5 Hydro / NDE witness / final dimensional
3 Aug 2026 Aftab Rahman Manufacturing 3.0
31 Jul 2026 Tomislav Simić Manufacturing 3.0
30 Jul 2026 Pavlo Koval Manufacturing 3.0
29 Jul 2026 Brett Murray Manufacturing 3.5
29 Jul 2026 Liam Farrell Manufacturing 8.0
28 Jul 2026 Marcus Keane Manufacturing 2.5
28 Jul 2026 Aftab Rahman Manufacturing 8.0
Material bought against this job
The job carries the commitment from the day the order goes out, not the day the bill arrives.
Purchasing
Budget
$8,870
Committed
$8,380
Received
$8,380
Billed
$8,380
Against budget
$-490
ItemSpecificationQtyBudget
PL-CS-10Plate 10mm A516 Gr70 PVQ ASTM A516 Gr70 N · heat B-771204 18 m² $3,348
HD-CS-711Dished end 711NB A516-70 2:1 SE AS 1210 / ASME · heat SDH-40772 2 ea $2,560
FL-CS-300Flange 300NB WN A105 Cl300 RF ASME B16.5 · heat EZ-99118 6 ea $2,472
CN-CS-12Welding wire 1.2mm ER70S-6 — 15kg AWS A5.18 5 spool $490
OrderSupplierPromisedOrderedReceivedStatus
PO-26-0436 BlueScope Distribution 19 Jun 2026 on time $3,348 $3,348 Billed
PO-26-0437 Southern Dished Heads 5 Jul 2026 on time $2,560 $2,560 Billed
PO-26-0439 Ezyflange Australia 18 Jun 2026 on time $2,472 $2,472 Billed
Supplier billTheir refOrderedReceivedBilledMatch
SB-26-0919PO-26-0436 BSD-771902 $3,348 $3,348 $3,348 Paid
SB-26-0921PO-26-0437 SDH-77518 $2,560 $2,560 $2,560 Paid
SB-26-0923PO-26-0439 EZ-221104 $2,472 $2,472 $2,472 Paid
Paying the supplier happens through the job, so the cost lands on the job that caused it rather than in a general overhead bucket at the end of the month.
Quality
Register
NCRRaisedDispositionReworkStatus
NCR-2026-025Undercut on nozzle N2 saddle weld 9 Jul 2026 Repair 4.0 h closed
ITP-174287 rev A 3 of 6 signed
1.1 Material identification & mill certificate review passed
2.1 Shell seam RT, 25% passed
3.1 MT — nozzle attachment welds passed
4.1 Hydrostatic test @ 1.43 x design witness
5.1 Final dimensional & nameplate pending
6.1 Manufacturer's Data Report compilation pending
Data report compiling — 5 of 9 sections complete .
Invoiced
$0 of $59,710
Nothing invoiced against this job yet.
Customer
Cold Logic
Contact
Nadia Fournier · nadia.f@coldlogic.com.au
Terms
30 days
Opened
8 Jun 2026
Promised
12 Aug 2026
Hydro
11 Aug 2026