JN 174298 In manufacture Serial BJ-26-0298
Reactor vessel 1200NB x 2400H SS316L · Viva Energy Refining · customer PO VE-PO-88214 · AS 1210 Cl 2A · SS316L · 100% NDE · witnessed by Bureau Veritas
Contract value
$144,145
Ex GST
Progress
74%
Earned $106,668
Cost to date
$75,094
Labour $42,836 · material $32,258
Margin at completion
35.6%
$51,322 · 609.3 h forecast
Promised
28 Aug 2026
19 days to go
Hours
Quoted in two buckets and booked in the same two. Nothing routes through a work centre.
Manufacturing MFG Direct
406.1 of 669.0 h
Expected 495.1 h at 74% complete ·
-89.0 h
Testing TEST Direct
39.8 of 74.0 h
Expected 54.8 h at 74% complete ·
-15.0 h
Rework RWK Indirect
5.0 h
Named against this job so you can see it, charged against neither bucket so it never flatters the quote.
-104.0 h against expected Total direct booked 445.9 h of 743.0 h quoted.
| Date | Who | Category | Hours | Note |
|---|---|---|---|---|
| 6 Aug 2026 | Pavlo Koval | Manufacturing | 8.5 | — |
| 6 Aug 2026 | Liam Farrell | Manufacturing | 7.0 | — |
| 5 Aug 2026 | David Nguyen | Testing | 4.0 | Hydro / NDE witness / final dimensional |
| 5 Aug 2026 | Ross Taylor | Manufacturing | 2.5 | — |
| 5 Aug 2026 | Pavlo Koval | Manufacturing | 3.0 | — |
| 5 Aug 2026 | Tomislav Simić | Manufacturing | 5.0 | — |
| 5 Aug 2026 | Liam Farrell | Manufacturing | 4.0 | — |
| 4 Aug 2026 | Marcus Keane | Manufacturing | 7.0 | — |
| 4 Aug 2026 | Aftab Rahman | Manufacturing | 3.0 | — |
| 4 Aug 2026 | Craig Carter | Manufacturing | 8.0 | — |
| 4 Aug 2026 | Michael Okafor | Manufacturing | 2.5 | — |
| 31 Jul 2026 | Marcus Keane | Manufacturing | 2.0 | — |
| 31 Jul 2026 | Ross Taylor | Manufacturing | 3.0 | — |
| 31 Jul 2026 | Tomislav Simić | Manufacturing | 4.0 | — |
Material bought against this job
The job carries the commitment from the day the order goes out, not the day the bill arrives.
Budget
$34,202
Committed
$34,938
Received
$32,258
Billed
$28,980
Against budget
+$736
| Item | Specification | Qty | Budget |
|---|---|---|---|
| PL-316-12Plate 12mm SS316L | ASTM A240 316L · heat H-2215044 | 34 m² | $18,972 |
| HD-316-1200Dished end 1200NB SS316L 2:1 SE | AS 1210 / ASME · heat SDH-40903 | 2 ea | $6,840 |
| FL-316-200Flange 200NB WN SS316L Cl300 RF | ASME B16.5 · heat EZ-99304 | 6 ea | $3,168 |
| PI-316-100Pipe 100NB Sch40S SS316L | ASTM A312 TP316L · heat PV-55219 | 22 m | $3,278 |
| CN-316-12Welding wire 1.2mm ER316LSi — 15kg | AWS A5.9 | 6 spool | $1,944 |
| Order | Supplier | Promised | Ordered | Received | Status | |
|---|---|---|---|---|---|---|
| PO-26-0421 | Atlas Steels | 15 Jun 2026 on time | $18,972 | $18,972 | Billed | |
| PO-26-0422 | Southern Dished Heads | 28 Jun 2026 2 d late | $6,840 | $6,840 | Billed | |
| PO-26-0424 | Ezyflange Australia | 11 Jun 2026 on time | $3,168 | $3,168 | Billed | |
| PO-26-0427 | Pipe & Valve Supplies | 17 Jun 2026 on time | $3,278 | $3,278 | Received | |
| PO-26-0464 | Bureau Veritas | 19 Aug 2026 | $2,680 | $0 | Ordered |
| Supplier bill | Their ref | Ordered | Received | Billed | Match | |
|---|---|---|---|---|---|---|
| SB-26-0902PO-26-0421 | AT-449012 | $18,972 | $18,972 | $18,972 | Paid | |
| SB-26-0905PO-26-0422 | SDH-77401 | $6,840 | $6,840 | $6,840 | Paid | |
| SB-26-0908PO-26-0424 | EZ-220914 | $3,168 | $3,168 | $3,168 | Paid |
Paying the supplier happens through the job, so the cost lands on the job that caused it rather than in a
general overhead bucket at the end of the month.
Quality
Register | NCR | Raised | Disposition | Rework | Status |
|---|---|---|---|---|
| NCR-2026-029Nozzle N4 projection 8mm over drawing | 29 Jul 2026 | Use as is | — | verify |
ITP-174298 rev A 4 of 9 signed
1.1 Material identification & mill certificate review passed
2.1 Welder qualification currency check passed
3.1 Shell seam RT, 100% passed
4.1 Nozzle set-out dimensional failed
5.1 PT — internal attachment welds passed
6.1 Hydrostatic test @ 1.43 x design witness
Invoiced
$72,073 of $144,145 | Invoice | Stage | Due | Ex GST | Status |
|---|---|---|---|---|
| INV-10901 | Progress claim 1 — 50% | 29 Aug 2026 | $72,073 | Sent |
- Customer
- Viva Energy Refining
- Contact
- Tanya Kowalski · tanya.kowalski@vivaenergy.com.au
- Terms
- 45 EOM
- Opened
- 1 Jun 2026
- Promised
- 28 Aug 2026
Insulated 150mm Rockwool, 0.6mm aluminium clad. Same build as the NZ PECPR reactor.