JN 174316 On hold
Fuel loading skid — vapour recovery · Liquip International · customer PO LIQ-2026-118 · AS 1210 Cl 2B · A516-70 / SS316L · 25% NDE
⏸
On hold
Customer holding for revised P&ID rev C. Material called off, labour stood down 24 Jul.
Contract value
$107,293
Ex GST
Progress
22%
Earned $23,604
Cost to date
$3,949
Labour $0 · material $3,949
Margin at completion
83.3%
$89,341 · 0.0 h forecast
Promised
2 Oct 2026
54 days to go
Hours
Quoted in two buckets and booked in the same two. Nothing routes through a work centre.
Manufacturing MFG Direct
0.0 of 550.0 h
Expected 121.0 h at 22% complete ·
-121.0 h
Testing TEST Direct
0.0 of 64.0 h
Expected 14.1 h at 22% complete ·
-14.1 h
Rework RWK Indirect
0.0 h
Named against this job so you can see it, charged against neither bucket so it never flatters the quote.
-135.1 h against expected Total direct booked 0.0 h of 614.0 h quoted.
Material bought against this job
The job carries the commitment from the day the order goes out, not the day the bill arrives.
Budget
$17,952
Committed
$0
Received
$0
Billed
$0
Against budget
$-17,952
| Item | Specification | Qty | Budget |
|---|---|---|---|
| PI-CS-150Pipe 150NB Sch40 CS | ASTM A106 Gr B · heat PV-55104 | 96 m | $8,304 |
| FL-CS-300Flange 300NB WN A105 Cl300 RF | ASME B16.5 · heat EZ-99118 | 18 ea | $7,416 |
| PL-CS-10Plate 10mm A516 Gr70 PVQ | ASTM A516 Gr70 N · heat B-771204 | 12 m² | $2,232 |
Paying the supplier happens through the job, so the cost lands on the job that caused it rather than in a
general overhead bucket at the end of the month.
Quality
Register | NCR | Raised | Disposition | Rework | Status |
|---|---|---|---|---|
| NCR-2026-023P&ID revision issued after fabrication release | 26 Jun 2026 | — | — | closed |
Invoiced
$0 of $107,293 Nothing invoiced against this job yet.
- Customer
- Liquip International
- Contact
- Sam Karadag · s.karadag@liquip.com
- Terms
- 30 days
- Opened
- 29 Jun 2026
- Promised
- 2 Oct 2026