JN 174338 In manufacture Serial BJ-26-0338
Blast chiller vessel 900NB — Kilsyth · Scott Automation · customer PO SCOTT-99117 · AS 1210 Cl 2A · SS304L · 20% NDE
Contract value
$57,161
Ex GST
Progress
31%
Earned $17,720
Cost to date
$15,795
Labour $7,695 · material $8,100
Margin at completion
35.5%
$20,308 · 261.3 h forecast
Promised
18 Sep 2026
40 days to go
Hours
Quoted in two buckets and booked in the same two. Nothing routes through a work centre.
Manufacturing MFG Direct
63.5 of 262.0 h
Expected 81.2 h at 31% complete ·
-17.7 h
Testing TEST Direct
11.5 of 35.0 h
Expected 10.9 h at 31% complete ·
+0.6 h
Rework RWK Indirect
6.0 h
Named against this job so you can see it, charged against neither bucket so it never flatters the quote.
-17.1 h against expected Total direct booked 75.0 h of 297.0 h quoted.
| Date | Who | Category | Hours | Note |
|---|---|---|---|---|
| 7 Aug 2026 | Ross Taylor | Manufacturing | 6.5 | — |
| 5 Aug 2026 | Craig Carter | Manufacturing | 6.0 | — |
| 5 Aug 2026 | Liam Farrell | Rework | 3.0 | Weld repair / re-work to NCR |
| 30 Jul 2026 | Michael Okafor | Manufacturing | 5.0 | — |
| 27 Jul 2026 | Liam Farrell | Manufacturing | 3.5 | — |
| 24 Jul 2026 | Brett Murray | Manufacturing | 5.0 | — |
| 23 Jul 2026 | Harpreet Singh | Manufacturing | 2.0 | — |
| 22 Jul 2026 | Ross Taylor | Manufacturing | 7.5 | — |
| 22 Jul 2026 | Tomislav Simić | Rework | 3.0 | Weld repair / re-work to NCR |
| 22 Jul 2026 | Liam Farrell | Manufacturing | 8.0 | — |
| 16 Jul 2026 | Liam Farrell | Manufacturing | 8.5 | — |
| 9 Jul 2026 | David Nguyen | Testing | 4.5 | Hydro / NDE witness / final dimensional |
| 9 Jul 2026 | Ross Taylor | Manufacturing | 1.5 | — |
| 9 Jul 2026 | Pavlo Koval | Manufacturing | 7.0 | — |
Material bought against this job
The job carries the commitment from the day the order goes out, not the day the bill arrives.
Budget
$12,030
Committed
$9,960
Received
$8,100
Billed
$6,240
Against budget
$-2,070
| Item | Specification | Qty | Budget |
|---|---|---|---|
| PL-304-08Plate 8mm SS304L | ASTM A240 304L · heat H-2213980 | 20 m² | $6,240 |
| HD-316-800Dished end 800NB SS316L 2:1 SE | AS 1210 / ASME · heat SDH-40881 | 2 ea | $3,720 |
| FL-316-150Flange 150NB WN SS316L Cl300 RF | ASME B16.5 · heat EZ-99231 | 6 ea | $2,070 |
| Order | Supplier | Promised | Ordered | Received | Status | |
|---|---|---|---|---|---|---|
| PO-26-0455 | Atlas Steels | 20 Jul 2026 on time | $6,240 | $6,240 | Billed | |
| PO-26-0456 | Southern Dished Heads | 3 Aug 2026 | $3,720 | $1,860 | Part received |
| Supplier bill | Their ref | Ordered | Received | Billed | Match | |
|---|---|---|---|---|---|---|
| SB-26-0937PO-26-0455 | AT-452004 | $6,240 | $6,240 | $6,240 | Matched — ready to pay |
Paying the supplier happens through the job, so the cost lands on the job that caused it rather than in a
general overhead bucket at the end of the month.
Quality
Register | NCR | Raised | Disposition | Rework | Status |
|---|---|---|---|---|
| NCR-2026-026Dished end delivered short — 1 of 2 | 15 Jul 2026 | — | — | open |
Invoiced
$0 of $57,161 Nothing invoiced against this job yet.
- Customer
- Scott Automation
- Contact
- Wesley Fung · w.fung@scottautomation.com
- Terms
- 30 days
- Opened
- 6 Jul 2026
- Promised
- 18 Sep 2026