Q-26-0112 Expired
Gas plant filter separator 1200NB · Origin Energy · valid until 26 Jun 2026
Accepting this quotation opens a job on the next JN number and carries the
461.0 h manufacturing and 54.0 h testing straight
across as the quoted hours. Nothing is re-keyed and nothing is re-estimated.
britannia:jahco
engineered for safety · built for pressure
Britannia Jahco Australia Pty Ltd
18 Healey Road, Dandenong South VIC 3175
ABN 13 141 068 171 · +61 3 9580 5599
ISO 9001 · LRQA
18 Healey Road, Dandenong South VIC 3175
ABN 13 141 068 171 · +61 3 9580 5599
ISO 9001 · LRQA
QUOTATION
Q-26-0112
Issued 12 May 2026
Valid until 26 Jun 2026
Estimator Andre Voss
Valid until 26 Jun 2026
Estimator Andre Voss
Quotation to
Origin Energy
Priya Naidu
priya.naidu@originenergy.com.au
Brisbane QLD
ABN 30 000 051 696
priya.naidu@originenergy.com.au
Brisbane QLD
ABN 30 000 051 696
Scope
Gas plant filter separator 1200NB
Design code AS 1210 Cl 1
Material A516-70
Payment terms 30 days
Material A516-70
Payment terms 30 days
| Description | Qty | Rate | Amount |
|---|---|---|---|
| Design, drafting & AS 1210 calculations | 1 | $4,248.00 | $4,248.00 |
| Manufacturing — 461 h | 461.0 | $135.00 | $62,235.00 |
| Testing, NDE & documentation — 54 h | 54.0 | $145.00 | $7,830.00 |
| Material, bought-in items & outside processes | 1 | $29,568.00 | $29,568.00 |
Subtotal ex GST$103,881.00
GST 10%$10,388.10
Total inc GST$114,269.10
Terms. Price firm to 26 Jun 2026 and subject to
material availability at the time of order. Design, fabrication, inspection and testing to AS 1210 Cl 1.
A manufacturer's data report is supplied on completion, including material certificates, welding procedures
and welder qualifications, NDE reports, heat treatment records and the hydrostatic test certificate.
Third-party inspection where the class requires it. Delivery ex works Dandenong South unless agreed
otherwise. All work carried out under our ISO 9001 · LRQA quality system.
Build-up
Internal — not on the document the customer sees
Manufacturing
461.0 h
Direct
Testing
54.0 h
Direct
Material cost
$26,400
Total cost
$75,325
Sell ex GST
$103,881
Gross margin
$28,556
Labour is costed at the blended shop rate and sold at the charge rate. Because the quote is built in the same