JN 174321 Demo Milk powder plant heat recovery unit
ISO 9001 · LRQA Sun 9 Aug 2026
JN 174321 In manufacture Serial BJ-26-0321

Milk powder plant heat recovery unit · Nestlé Australia · customer PO NEST-773401 · AS 1210 Cl 2A · SS304L · 20% NDE

From Q-26-0124
Contract value
$121,329
Ex GST
Progress
48%
Earned $58,238
Cost to date
$46,702
Labour $22,990 · material $23,712
Margin at completion
30.9%
$37,535 · 504.2 h forecast
Promised
11 Sep 2026
33 days to go
Hours
Quoted in two buckets and booked in the same two. Nothing routes through a work centre.
Labour
Manufacturing MFG Direct
213.5 of 499.0 h
Expected 239.5 h at 48% complete · -26.0 h
Testing TEST Direct
20.0 of 61.0 h
Expected 29.3 h at 48% complete · -9.3 h
Rework RWK Indirect
8.5 h
Named against this job so you can see it, charged against neither bucket so it never flatters the quote.
-35.3 h against expected Total direct booked 233.5 h of 560.0 h quoted.
DateWhoCategoryHoursNote
7 Aug 2026 Pavlo Koval Manufacturing 6.0
6 Aug 2026 Aftab Rahman Manufacturing 7.0
6 Aug 2026 Michael Okafor Manufacturing 3.5
4 Aug 2026 Pavlo Koval Manufacturing 4.5
4 Aug 2026 Brett Murray Manufacturing 5.5
3 Aug 2026 David Nguyen Testing 3.0 Hydro / NDE witness / final dimensional
3 Aug 2026 Ross Taylor Manufacturing 7.5
31 Jul 2026 David Nguyen Testing 2.5 Hydro / NDE witness / final dimensional
31 Jul 2026 Aftab Rahman Manufacturing 8.5
31 Jul 2026 Craig Carter Manufacturing 7.5
31 Jul 2026 Liam Farrell Rework 5.0 Weld repair / re-work to NCR
30 Jul 2026 Brett Murray Manufacturing 1.5
29 Jul 2026 Aftab Rahman Manufacturing 5.0
29 Jul 2026 Harpreet Singh Manufacturing 7.5
Material bought against this job
The job carries the commitment from the day the order goes out, not the day the bill arrives.
Purchasing
Budget
$35,898
Committed
$34,608
Received
$23,712
Billed
$8,736
Against budget
$-1,290
ItemSpecificationQtyBudget
PL-304-08Plate 8mm SS304L ASTM A240 304L · heat H-2213980 28 m² $8,736
TU-316-2540Tube 25.4 x 2.11 SS316L seamless ASTM A213 TP316L · heat SV-884219 380 m $23,712
FL-316-150Flange 150NB WN SS316L Cl300 RF ASME B16.5 · heat EZ-99231 10 ea $3,450
OrderSupplierPromisedOrderedReceivedStatus
PO-26-0446 Atlas Steels 29 Jun 2026 on time $8,736 $8,736 Billed
PO-26-0447 Sandvik Materials Technology 24 Aug 2026 $23,712 $14,976 Part received
PO-26-0466 Blast & Paint Solutions 21 Aug 2026 $2,160 $0 Ordered
Supplier billTheir refOrderedReceivedBilledMatch
SB-26-0928PO-26-0446 AT-451220 $8,736 $8,736 $8,736 Paid
Paying the supplier happens through the job, so the cost lands on the job that caused it rather than in a general overhead bucket at the end of the month.
Quality
Register
NCRRaisedDispositionReworkStatus
NCR-2026-027Baffle spacing 12mm out at positions 4 and 5 18 Jul 2026 Rework 8.0 h closed
Invoiced
$48,531 of $121,329
InvoiceStageDueEx GSTStatus
INV-10905 Progress claim 1 — 40% 11 Sep 2026 $48,531 Sent
Customer
Nestlé Australia
Contact
Marina Bosco · marina.bosco@au.nestle.com
Terms
30 days
Opened
15 Jun 2026
Promised
11 Sep 2026