JN 174331 In test Serial BJ-26-0331
Wort cooler bundle replacement — Abbotsford · Carlton & United Breweries · customer PO CUB-461902 · AS 1210 Cl 2B · TEMA AES · SS316L · 10% NDE
Contract value
$63,032
Ex GST
Progress
94%
Earned $59,250
Cost to date
$42,268
Labour $22,468 · material $19,800
Margin at completion
30.7%
$19,330 · 251.6 h forecast
Promised
14 Aug 2026
5 days to go
Hours
Quoted in two buckets and booked in the same two. Nothing routes through a work centre.
Manufacturing MFG Direct
203.5 of 237.0 h
Expected 222.8 h at 94% complete ·
-19.3 h
Testing TEST Direct
23.5 of 35.0 h
Expected 32.9 h at 94% complete ·
-9.4 h
Rework RWK Indirect
9.5 h
Named against this job so you can see it, charged against neither bucket so it never flatters the quote.
-28.7 h against expected Total direct booked 227.0 h of 272.0 h quoted.
| Date | Who | Category | Hours | Note |
|---|---|---|---|---|
| 7 Aug 2026 | Michael Okafor | Manufacturing | 3.0 | — |
| 5 Aug 2026 | Marcus Keane | Manufacturing | 7.0 | — |
| 4 Aug 2026 | Harpreet Singh | Manufacturing | 8.5 | — |
| 3 Aug 2026 | Aftab Rahman | Manufacturing | 4.0 | — |
| 3 Aug 2026 | Harpreet Singh | Manufacturing | 8.0 | — |
| 31 Jul 2026 | Pavlo Koval | Rework | 4.0 | Weld repair / re-work to NCR |
| 31 Jul 2026 | Pavlo Koval | Manufacturing | 2.0 | — |
| 30 Jul 2026 | Marcus Keane | Manufacturing | 8.5 | — |
| 30 Jul 2026 | Craig Carter | Manufacturing | 6.0 | — |
| 30 Jul 2026 | Liam Farrell | Manufacturing | 6.5 | — |
| 30 Jul 2026 | Harpreet Singh | Manufacturing | 3.5 | — |
| 30 Jul 2026 | Harpreet Singh | Manufacturing | 2.0 | — |
| 29 Jul 2026 | David Nguyen | Rework | 4.0 | Weld repair / re-work to NCR |
| 29 Jul 2026 | Brett Murray | Manufacturing | 2.0 | — |
Material bought against this job
The job carries the commitment from the day the order goes out, not the day the bill arrives.
Budget
$19,800
Committed
$19,800
Received
$19,800
Billed
$19,800
Against budget
$0
| Item | Specification | Qty | Budget |
|---|---|---|---|
| TU-316-1905Tube 19.05 x 1.65 SS316L seamless | ASTM A213 TP316L · heat SV-884120 | 420 m | $17,556 |
| PL-316-10Plate 10mm SS316L | ASTM A240 316L · heat H-2214902 | 4 m² | $1,856 |
| GK-SW-150Gasket 150NB spiral wound 316/graphite | ASME B16.20 | 8 ea | $388 |
| Order | Supplier | Promised | Ordered | Received | Status | |
|---|---|---|---|---|---|---|
| PO-26-0431 | Sandvik Materials Technology | 30 Jul 2026 on time | $17,556 | $17,556 | Billed | |
| PO-26-0433 | Atlas Steels | 6 Jul 2026 on time | $1,856 | $1,856 | Billed | |
| PO-26-0474 | Gasket Solutions Australia | 8 Aug 2026 on time | $388 | $388 | Received |
| Supplier bill | Their ref | Ordered | Received | Billed | Match | |
|---|---|---|---|---|---|---|
| SB-26-0914PO-26-0431 | SV-1180229 | $17,556 | $17,556 | $17,556 | Matched — ready to pay | |
| SB-26-0916PO-26-0433 | AT-450887 | $1,856 | $1,856 | $1,856 | Paid | |
| SB-26-0951PO-26-0474 | GSA-33107 | $388 | $388 | $388 | Awaiting match |
Paying the supplier happens through the job, so the cost lands on the job that caused it rather than in a
general overhead bucket at the end of the month.
Quality
Register | NCR | Raised | Disposition | Rework | Status |
|---|---|---|---|---|
| NCR-2026-028Two tube-to-tubesheet joints leaking at first hydro | 24 Jul 2026 | Rework | 6.0 h | closed |
ITP-174331 rev A 3 of 5 signed
1.1 Tube material certificate review passed
2.1 Tube expanding torque record passed
3.1 Hydrostatic test @ 1.43 x design passed
4.1 Final dimensional & nameplate pending
5.1 Manufacturer's Data Report compilation pending
Data report compiling —
6 of 9 sections complete
.
Invoiced
$0 of $63,032 Nothing invoiced against this job yet.
- Customer
- Carlton & United Breweries
- Contact
- Josh Wexler · josh.wexler@cub.com.au
- Terms
- 30 days
- Opened
- 22 Jun 2026
- Promised
- 14 Aug 2026
- Hydro
- 10 Aug 2026
Brewery shut window is fixed — 14 August or it waits until November.