JN 174344 Planning
Hydrogen separator skid — 2 off · Hydrogen Renewables Australia · customer PO H2RA-0091 · AS 1210 Cl 1 · Duplex 2205 · 100% NDE · witnessed by Bureau Veritas
Contract value
$304,750
Ex GST
Progress
6%
Earned $18,285
Cost to date
$8,335
Labour $3,800 · material $4,535
Margin at completion
26.5%
$80,780 · 1,562.0 h forecast
Promised
18 Dec 2026
131 days to go
Hours
Quoted in two buckets and booked in the same two. Nothing routes through a work centre.
Manufacturing MFG Direct
40.0 of 1,408.0 h
Expected 84.5 h at 6% complete ·
-44.5 h
Testing TEST Direct
0.0 of 154.0 h
Expected 9.2 h at 6% complete ·
-9.2 h
Rework RWK Indirect
0.0 h
Named against this job so you can see it, charged against neither bucket so it never flatters the quote.
-53.7 h against expected Total direct booked 40.0 h of 1,562.0 h quoted.
| Date | Who | Category | Hours | Note |
|---|---|---|---|---|
| 6 Aug 2026 | Tomislav Simić | Manufacturing | 4.0 | — |
| 5 Aug 2026 | Brett Murray | Manufacturing | 2.5 | — |
| 4 Aug 2026 | Liam Farrell | Manufacturing | 8.0 | — |
| 3 Aug 2026 | Marcus Keane | Manufacturing | 5.0 | — |
| 3 Aug 2026 | Liam Farrell | Manufacturing | 8.0 | — |
| 31 Jul 2026 | Brett Murray | Manufacturing | 6.5 | — |
| 30 Jul 2026 | Brett Murray | Manufacturing | 2.0 | — |
| 28 Jul 2026 | Harpreet Singh | Manufacturing | 4.0 | — |
Material bought against this job
The job carries the commitment from the day the order goes out, not the day the bill arrives.
Budget
$75,580
Committed
$73,640
Received
$0
Billed
$0
Against budget
$-1,940
| Item | Specification | Qty | Budget |
|---|---|---|---|
| PL-DX-10Plate 10mm Duplex 2205 | ASTM A240 UNS S32205 · heat H-2216221 | 42 m² | $37,128 |
| PI-316-100Pipe 100NB Sch40S SS316L | ASTM A312 TP316L · heat PV-55219 | 160 m | $23,840 |
| FL-316-200Flange 200NB WN SS316L Cl300 RF | ASME B16.5 · heat EZ-99304 | 24 ea | $12,672 |
| GK-SW-150Gasket 150NB spiral wound 316/graphite | ASME B16.20 | 40 ea | $1,940 |
| Order | Supplier | Promised | Ordered | Received | Status | |
|---|---|---|---|---|---|---|
| PO-26-0442 | Atlas Steels | 2 Sep 2026 | $37,128 | $0 | Ordered | |
| PO-26-0443 | Pipe & Valve Supplies | 14 Aug 2026 | $23,840 | $0 | Ordered | |
| PO-26-0444 | Ezyflange Australia | 20 Aug 2026 | $12,672 | $0 | Draft |
Paying the supplier happens through the job, so the cost lands on the job that caused it rather than in a
general overhead bucket at the end of the month.
Quality
Register No non-conformances raised on this job.
Invoiced
$0 of $304,750 | Invoice | Stage | Due | Ex GST | Status |
|---|---|---|---|---|
| INV-10903 | Progress claim 1 — 25% on order | 22 Sep 2026 | $76,188 | Draft |
- Customer
- Hydrogen Renewables Australia
- Contact
- Elena Marchetti · e.marchetti@h2ra.com.au
- Terms
- 30 days
- Opened
- 28 Jul 2026
- Promised
- 18 Dec 2026
Duplex plate on 34-day lead. First hydrogen job — welder quals to be extended to duplex before fit-up.