NCR-2026-024 Closed Customer
Customer witness unavailable at nominated hold point
What was found
Incitec Pivot inspector did not attend the notified hydro on 30 June. Test held over four days.
Corrective action
Hold point notification lead time extended from 5 to 10 working days for all witnessed tests.
Raised by David Nguyen, QA / Test Coordinator, on 30 Jun 2026 · closed 8 Jul 2026.
Detail
- Job
- JN 174276
- Customer
- Incitec Pivot Fertilisers
- Source
- Customer
- Cause
- Customer — hold point
- Disposition
- —
- Rework
- None
- Cost
- —
Rework hours are booked to the Rework category, which is indirect. They name this job so
the cost is attributable, and they never touch the job's quoted manufacturing or testing hours.