JN 174276 Despatched Serial BJ-26-0276
Ammonia condenser bundle — Geelong · Incitec Pivot Fertilisers · customer PO IPF-556218 · AS 1210 Cl 2B · TEMA AEU · SS316L · 25% NDE
Contract value
$76,203
Ex GST
Progress
100%
Earned $76,203
Cost to date
$49,002
Labour $22,810 · material $26,192
Margin at completion
35.7%
$27,202 · 240.1 h forecast
Promised
24 Jul 2026
Despatched 22 Jul 2026
Hours
Quoted in two buckets and booked in the same two. Nothing routes through a work centre.
Manufacturing MFG Direct
200.9 of 275.0 h
Expected 275.0 h at 100% complete ·
-74.1 h
Testing TEST Direct
34.7 of 38.0 h
Expected 38.0 h at 100% complete ·
-3.3 h
Rework RWK Indirect
4.5 h
Named against this job so you can see it, charged against neither bucket so it never flatters the quote.
-77.4 h against expected Total direct booked 235.6 h of 313.0 h quoted.
| Date | Who | Category | Hours | Note |
|---|---|---|---|---|
| 20 Jul 2026 | Craig Carter | Manufacturing | 4.0 | — |
| 17 Jul 2026 | Harpreet Singh | Rework | 3.5 | Weld repair / re-work to NCR |
| 16 Jul 2026 | Michael Okafor | Manufacturing | 2.0 | — |
| 15 Jul 2026 | Tomislav Simić | Manufacturing | 8.0 | — |
| 13 Jul 2026 | David Nguyen | Testing | 2.5 | Hydro / NDE witness / final dimensional |
| 10 Jul 2026 | Marcus Keane | Manufacturing | 7.0 | — |
| 10 Jul 2026 | Brett Murray | Rework | 1.0 | Weld repair / re-work to NCR |
| 2 Jul 2026 | Ross Taylor | Manufacturing | 8.5 | — |
| 29 Jun 2026 | Ross Taylor | Manufacturing | 4.5 | — |
| 29 Jun 2026 | Aftab Rahman | Manufacturing | 5.0 | — |
| 25 Jun 2026 | Aftab Rahman | Manufacturing | 5.0 | — |
| 24 Jun 2026 | Tomislav Simić | Manufacturing | 5.0 | — |
| 23 Jun 2026 | Marcus Keane | Manufacturing | 8.0 | — |
| 23 Jun 2026 | Craig Carter | Manufacturing | 3.0 | — |
Material bought against this job
The job carries the commitment from the day the order goes out, not the day the bill arrives.
Budget
$26,192
Committed
$0
Received
$0
Billed
$0
Against budget
$-26,192
| Item | Specification | Qty | Budget |
|---|---|---|---|
| TU-316-1905Tube 19.05 x 1.65 SS316L seamless | ASTM A213 TP316L · heat SV-884120 | 560 m | $23,408 |
| PL-316-10Plate 10mm SS316L | ASTM A240 316L · heat H-2214902 | 6 m² | $2,784 |
Paying the supplier happens through the job, so the cost lands on the job that caused it rather than in a
general overhead bucket at the end of the month.
Quality
Register | NCR | Raised | Disposition | Rework | Status |
|---|---|---|---|---|
| NCR-2026-024Customer witness unavailable at nominated hold point | 30 Jun 2026 | — | — | closed |
Data report issued 22 Jul 2026 —
9 of 9 sections complete
· registration VIC-PE-118041.
Invoiced
$76,203 of $76,203 | Invoice | Stage | Due | Ex GST | Status |
|---|---|---|---|---|
| INV-10896 | Final | 6 Sep 2026 | $76,203 | Sent |
- Customer
- Incitec Pivot Fertilisers
- Contact
- Robert Nyman · robert.nyman@incitecpivot.com.au
- Terms
- 30 days
- Opened
- 4 May 2026
- Promised
- 24 Jul 2026
- Hydro
- 18 Jul 2026
- Despatched
- 22 Jul 2026